OverviewThere is no way the PIC's could have seen any current' was the gist of Mike Griffin's assessment. Griffin was the NASA Administrator at the time. The buck stopped at his desk. Holding a napkin out to Pat Lampton, Griffin showed Lampton the calculations he'd made over dinner that predicted that the Pyrotechnic Initiator Controllers (PIC's) at the base of the Space Shuttle Solid Rocket Boosters (SRBs) were fine. A lightning strike the day before, the worst ever experienced with a Space Shuttle on the launch pad, caused a halt to the launch count down as technicians, engineers, and managers scrambled identify any damage to the launch system. SRB technicians and engineers assessed the data against their Lightning Strike Re-Test Requirements, determining that all but one of the requirements could be checked if they resumed the countdown. For the one remaining requirement, testing the integrity of the PIC's would require 96 hours to set up, test, and reassemble. The engineers were convinced that there was no way to do calculations to show the PIC's were okay. The only option was to stand down. It was SRB Deputy Project Manager (PM) Pat Lampton's responsibility to decide what the SRB project position needed to be to certify that their hardware was safe to fly. He had to communicate that decision to the Mission Management Team (MMT) as a Go or No Go position to resume the count down. If the answer was Go they could still meet a delayed, but acceptable launch schedule. If the answer was No Go, rescheduling the launch would be a grueling shuffling of hardware, personnel, and mission timelines to accommodate Russian missions to the Space Station, supplies for the launch, and personnel manning launch operations. On top of that, Hurricane Ernesto was spinning off the coast of Florida, threatening the need for the Shuttle to roll back to the hangar if they waited too long. Kummer, Lizette and Stevens, Jennifer Marshall Space Flight Center MSFC-CS1008-1, M17-6063 Full Product DetailsAuthor: National Aeronautics and Space Adm NasaPublisher: Independently Published Imprint: Independently Published Dimensions: Width: 21.60cm , Height: 0.20cm , Length: 27.90cm Weight: 0.091kg ISBN: 9781794438903ISBN 10: 1794438904 Pages: 28 Publication Date: 23 January 2019 Audience: General/trade , General Format: Paperback Publisher's Status: Active Availability: Available To Order ![]() We have confirmation that this item is in stock with the supplier. It will be ordered in for you and dispatched immediately. Table of ContentsReviewsAuthor InformationTab Content 6Author Website:Countries AvailableAll regions |